There are a number of main options within the NEC contract suite, which reflect different risk allocations between the parties. As part of its procurement strategy for a subcontract package, the contractor can select from fixed price contracts, to fully cost reimbursable options, such as:
NEC ECC Option C and E contracts tend to be the backbone (currently) of reimbursing high-risk infrastructure projects in the UK. Large value subcontractors are generally procured using back-to-back cost reimbursable options, but there will always be key subcontractors (and sub-subcontractors) engaged on priced options, Option A and Option B.
Option A or Option B subcontracts do not require the vigorous verification of detailed accounting records compared to open book defined cost based contracts. However, on one of these subcontracts, there are still some common-sense verification rules and basic principles to follow in order to accurately assess the Price for Work Done to Date (PWDD).
We try and keep it simple, using the acronym R.E.V.I.E.W, which offers pragmatic guidance on how to plan and deliver assurance work. This ensures the review process is concentrated on the right areas and people do not ask for onerous volumes of records without a focus on project or contract risks.
This paper is one of a series. This one focuses on Option A and Option B subcontract costs.
Whilst they are both priced options, the risks are managed differently between Option A and B. The quantities in relation to the works under an Option B are remeasured, whereas there is price fixity against the activities under an Option A.
If you are reviewing a reimbursable subcontract (Option C, D or E), our previous tip sheets on people, plant and materials, equipment etc, will aid your learning.
In case you missed the last blog or just need a quick memory jogger, the acronym R.E.V.I.E.W. should help your thought process when reviewing any cost element. Much of this goes to the heart of smart or risk based auditing.
R - Rules of the contract
A cost type is only allowable if it passes the reimbursement rules of the “specific” contract.
E - Environment
Understanding the importance of the operational and financial control environment in which costs are managed and presented is critically important to your assurance work. Be prepared to speak with project and finance team members (both client and supplier), walk the site and review key contract documentation to better understand the project set up.
V - Visualise data
Intelligent data analysis and visualisation are key tools to better understand how and where money has been spent.
I - Identify risk and design tests
A thorough understanding of the cost area being reviewed should emerge through the first three steps above. This will help flush out specific project and contract risks that require review. This will be over and above core transactions that will provide the bulk of your assurance.
E - Examine and evaluate accounts and records
A good open working relationship with the supplier being reviewed is essential to obtainings ource documents backing up the cost claimed. Throughout your work, make sure you regularly check back in with your client project manager and cost manager too.
W - Write up findings, draw conclusions and report
All examinations should follow a robust and formal recording and reporting process. No ifs, no buts. Always leave an audit trail of work completed and assurances obtained.
An Option A subcontract is a priced contract with an activity schedule (a series of tasks in effect rolling up to a fixed price lump sum). It is utilised by main contractors wishing to pass the whole estimating, pricing and efficiency risk to the subcontractor. Option A gives the contractor the most price certainty, assuming the design and scope is complete at the tender stage, prior to entering into contract. There will always be a risk of cost growth due to things changing or emerging; these will be managed as you would expect through the compensation event process (clause 60.1).
Payments are based on the subcontractor demonstrating completed activities. The assessment of the subcontractor’s application for payment is therefore easier, (in theory), and should take less commercial resource than other options.
Option B is slightly different in that prices are not agreed as a lump sum. The quantities are remeasured against the original bill of quantities. If quantities vary significantly, or there are scope changes, this may result in different rates or lump sums being agreed as compensation events.
Therefore, like Option A, it is important not to tender until the design is complete and there is certainty about the scope of works and quantities. This option is used when the contractor wishes to transfer the risks around productivity, (but not quantities), to the subcontractor.
Evaluating change on an Option A priced activity schedule should be a simpler process than an Option B bill of quantities. With Option B, the cost manager must assess if any changes to quantities should be priced using rates in the original bill of quantities or agreed as compensation events. This requires a remeasurement of the contract for each assessment period.
All too often, works increase significantly in comparison to the original scope. This results in overly complex quotation submissions and assessments, which may require significant increased resources from both parties to develop and agree upon.