Reimbursable contracts are commonly used in major construction programs today.
Currently, NEC ECC Option C and E contracts form the backbone of reimbursing high-risk infrastructure projects in the UK.
Within these contracts, the basic clauses permit project managers (often delegated to cost managers) to inspect accounts and records related to the claimed cost items. Z Clauses are frequently added to enable third-party or client auditors to conduct audits or verify supplier costs on an "as needed" basis.
Those suppliers being audited need to be helpful and transparent that’s pretty much it.
The audit side occasionally becomes overly complex, with onerous volumes of records being requested, meaningless conclusions drawn from samples and mischarges extrapolated aggressively (and often incorrectly).
We try and keep it simple, using the acronym R.E.V.I.E.W, which offers pragmatic guidance on how to plan and deliver assurance work.
This paper is one of a series of tip sheets – this one focusses in on costs relating to plant and materials.
In case you missed the last blog or just need a quick memory jogger, the acronym R.E.V.I.E.W. should help your thought process when reviewing any cost element. Much of this goes to the heart of smart or risk based auditing.
R - Rules of the contract
A cost type is only allowable if it passes the reimbursement rules of the “specific” contract.
E - Environment
Understanding the importance of the operational and financial control environment in which costs are managed and presented is critically important to your assurance work. Be prepared to speak with project and finance team members (both client and supplier), walk the site and review key contract documentation to better understand the project set up.
V - Visualise data
Intelligent data analysis and visualisation are key tools to better understand how and where money has been spent.
I - Identify risk and design tests
A thorough understanding of the cost area being reviewed should emerge through the first three steps above. This will help flush out specific project and contract risks that require review. This will be over and above core transactions that will provide the bulk of your assurance.
E - Examine and evaluate accounts and records
A good open working relationship with the supplier being reviewed is essential to obtainings ource documents backing up the cost claimed. Throughout your work, make sure you regularly check back in with your client project manager and cost manager too.
W - Write up findings, draw conclusions and report
All examinations should follow a robust and formal recording and reporting process. No ifs, no buts. Always leave an audit trail of work completed and assurances obtained.
So, let’s start our REVIEW process for plant and materials.
Under NEC contracts, plant and materials are basically items purchased by the contractor that are intended to be included in the works. There is a separate cost category for equipment, which is needed to “enable” the construction of the works.
Often there is confusion between plant and equipment, but equipment is ultimately removed from site.
Under the main reimbursable options, the contractor is paid for the cost of plant and materials ‘at open market or competitively tendered prices’ (see clause 52.1). In addition, the components for plant and materials are based on ‘open book’ principles and the accounts and records which support these costs can be inspected at any time (clause 52.4).
We would expect a contractor’s application for payment to be submitted monthly, supported by cost claims linked directly to a contract cost ledger report from its accounting system. This ledger report will show costed transactions for plant and material, referenced back to either delivery/receipt notes or formal invoice numbers.
A common mistake we often see relating to audits or inspections, is to start by simply selecting a large sample of costed transactions from the ledger report. In some cases, clients may even mandate assurance providers check 100% of all costs!
This paper sets out some basic guidance to a more pragmatic and effective approach to verifying plant and material costs. The challenge is how to provide high levels of assurance without checking every transaction.