Technology: Data centres | The 10 GW race will be decided on watts, not megawatts

By Rohan Lobo, Partner and Technology, Media & Telecom Industry leader, Deloitte South Asia

The bottom line

India’s data-centre capacity is expected to grow from about 1.8 GW1 today to as much as 10 GW by 20302. Most announcements and valuations still describe that growth in megawatts of facility capacity, rather than the computing capacity those megawatts can support.

A conventional data centre can operate at a Power Usage Effectiveness (PUE) of about 1.6, while a modern hyperscale facility can achieve 1.2 or lower3. For the same information technology load, a facility at PUE 1.6 requires about one-third more total power than one at PUE 1.24. Deloitte Global predicts that inference will account for roughly two-thirds of AI compute in 20265. As inference workloads recur with use, inefficient power consumption can increase the cost of delivering AI outcomes.

The priority is to move the next tranche of capital from land banks to power engineering. A 100 MW campus operating at PUE 1.256 supports 80 MW of information technology load, slightly more than a 130 MW rival operating at PUE 1.65, which supports about 78.8 MW of IT load. For comparable computing capacity, the more efficient campus needs about 23 percent less grid capacity. Its non-information-technology overhead is 20 MW rather than 51.2 MW.7

What has changed?

Demand is accelerating. India’s installed data-centre capacity is expected to reach as much as 10 GW by 2030. The Ministry of Power estimates that electricity demand from data centres will reach 13.56 GW by fiscal 2031–328. State policies, valuations and capacity announcements, however, continue to be framed largely in megawatts.

The workload is changing as well. Deloitte Global expects inference to account for roughly two-thirds of AI compute in 2026. Training is intensive but episodic. Inference recurs whenever a user, application or autonomous system uses a trained model. Aggregate inference spending can therefore rise even as the cost of an individual query falls. When customers measure economics in rupees per million tokens, the operator’s energy efficiency becomes part of the customer’s operating margin.

Why watts, not megawatts, decide the winner?

Reliable, cost-competitive power is becoming the scarcer input. A megawatt describes electrical capacity, but it does not indicate how much of that capacity reaches servers, accelerators, storage and networking equipment after accounting for cooling, electrical conversion, lighting and other facility requirements.

The shift towards inference makes recurring inefficiency commercially visible. PUE measures total facility energy relative to information technology energy. Each sustained increase of facility overhead adds to the operating bill. Hyperscalers and AI companies choosing an Indian provider may increasingly look beyond available megawatts to the energy required per unit of useful compute.

The sovereignty dividend accrues to efficient capacity. Deloitte Global’s 2026 TMT Predictions estimates that more than US$100 billion will be committed globally to Sovereign AI compute in 20269. The research also notes India’s pursuit of greater self-reliance across the technology stack through the India AI Mission and India Semiconductor Mission. Operators that can demonstrate competitive Indian compute should be better placed to attract that capital, and the investment case will depend on cooling design, renewable integration and grid engineering.

What does this mean for you?

If you allocate capital to data centres, re-weight the next tranche towards firm power, renewable procurement, storage, cooling efficiency and grid-interconnect engineering. Set a measurable annual PUE target in the investment memorandum and management scorecard. Separate facility capacity from information technology capacity in every investment case. When an operator pitches megawatts, ask what share of those watts reaches the chip.

 

What would change my mind?

If grid reform delivers abundant, inexpensive, firm power to the major data-centre clusters before 2028, the efficiency premium narrows and scale wins again. If inference moves to the edge faster than Deloitte Global expects, demand for centralised data centres softens10. Both developments should be monitored, but neither appears likely within the investment horizon for capital being committed today.

Calculation notes

  • PUE = total facility power ÷ information technology equipment power. Therefore, information technology load = facility power ÷ PUE.
  • At a fixed information technology load, 1.6 ÷ 1.2 = 1.333. A PUE 1.6 facility requires 33.3 percent more total facility power than one at PUE 1.2.
  • 100 MW ÷ 1.25 = 80.0 MW of information technology load; 130 MW ÷ 1.65 = 78.8 MW.
  • For comparable computing output, grid capacity falls from 130 MW to 100 MW: (130 − 100) ÷ 130 = 23.1 percent.
  • Non-information-technology overhead equals facility power minus information technology load: 20.0 MW versus 51.2 MW.
  • The comparison does not claim that PUE alone determines cooling-plant size, electrical-plant expenditure, processor utilisation, water consumption, resilience, or total life-cycle emissions.

Sources