From megawatts to margin: AI in the Gulf enters its second phase in 2027

ME PoV Issue 50

Subscribe to receive the Deloitte Middle East Point of View magazine

The capital is committed and the sites are secured. What decides returns now is the pace of the build, the depth of domestic demand, and how far up the value chain the region chooses to go.

476 MW

Saudi Arabia's operational data center capacity in the first quarter of 2026, having risen sevenfold since 2021

1.9 GW

HUMAIN's roadmap target by 2030, roughly four times the national installed base as it stands today

1 GW

Stargate UAE compute cluster within a five-gigawatt campus in Abu Dhabi

That distance is the most useful lens for understanding the Gulf technology sector as it enters 2027. It reflects neither a shortage of ambition nor a shortage of capital, both of which the region has demonstrated at a scale few others could match. It reflects the gap between capacity that has been announced and capacity that is built, commissioned and carrying customer load, a gap every market building at this pace is working through and one that the Gulf is closing faster than most.

Value in AI is concentrated at the two ends of the value chain

General-purpose AI models—the class of systems behind ChatGPT and its competitors—are quickly commoditizing, as they tend to converge quickly and capability gaps close within months. Margin is concentrated at the two ends of the chain: beneath the models, in chips, power, and data centers, and above them, in the applications and agents closest to the customer. The more difficult position to defend is in the middle, where a business owns a general-purpose model and little else.

The constraint runs across the whole infrastructure layer

Building AI capacity at gigawatt scale depends on a long chain of inputs, each carrying its own lead time and its own point of failure: advanced chips released under export license and delivered in tranches, land with grid access, high-voltage electrical equipment, cooling systems operating at power densities with limited industry precedent, and commissioning teams who have delivered facilities of this class before. Different inputs bind at different moments, and which one is binding changes by site and by quarter. A project can be fully funded, fully permitted, and still a year away from carrying load.

Access to computing has become an instrument of statecraft

Advanced computing is now allocated through government decisions as much as commercial ones. The United States approved G42's access to up to 35,000 NVIDIA GB300 chips, and NVIDIA's Saudi allocation began with a first tranche of 18,000 Blackwell units directed to HUMAIN.

By Hassan Malik, Partner and TMT Leader and Mirza Ali, Director, Monitor Deloitte, Deloitte Middle East

1. Fortune, “Saudi AI giant races to fund data center expansion”, 9 September 2026. https://fortune.com/2026/09/09/saudis-humain-turns-tooutside-investment-as-the-kingdom-reins-infiscal-spending/.

2. G42, “Global Tech Alliance Launches Stargate UAE”, 22 May 2025. https://www.g42.ai/resources/news/global-tech-alliance-launches-stargate-uae.

3. The National, “Stargate UAE’s first phase to be completed in third quarter of 2026”, 5 December 2025. https://www.thenationalnews.com/business/2025/12/05/stargate-uaes-first-phaseto-be-completed-in-third-quarter-of-2026/.

4. Together AI and HUMAIN, joint press release issued via Business Wire, 31 August 2026. https://finance.yahoo.com/technology/ai/articles/together-ai-humain-form-strategic-120000648.html.

5. Data Center Dynamics, “Humain secures 211 plots of land in Saudi Arabia for data centers”, 27 July 2026. https://www.datacenterdynamics.com/en/news/humain-secures-211-plots-of-land-insaudi-arabia-for-data-centers/.

6. Reuters, via Yahoo Finance, “Saudi’s Humainto launch data centers with US chips in early 2026, Bloomberg News reports”. https://finance.yahoo.com/news/saudis-humain-launch-datacenters-191120744.html.

7. The Standard, reporting Bloomberg, “US AI expansion hit by power shortages”. https://www.thestandard.com.hk/innovation/article/328687.

8. Reuters, “US power companies scramble to secure equipment as surging data center demand strains supplies”, 9 July 2026. https://www.kitco.com/news/off-the-wire/2026-07-09/us-powercompanies-scramble-secure-equipment-surgingdata-center.

9. Lawrence Berkeley National Laboratory, “QueuedUp: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection”. https://emp.lbl.gov/publications/queued-2025-editioncharacteristics.

10. Gulf Business, “Stargate UAE: G42, OpenAI, Oracle, NVIDIA, SoftBank, Cisco to build AIcluster”. https://gulfbusiness.com/g42-openaioracle-nvidia-to-build-stargate-uae/.

11. stc group, Investor Relations H1 2026 results presentation. https://www.stc.com/content/dam/groupsites/en/pdf/InvestorRelationsQ2-2026En.pdf.

12. Business Wire, “HUMAIN and Infra Announce AI and Digital Financing Framework Agreement”, 22 January 2026. https://www.businesswire.com/news/home/20260122600897/en/HUMAINand-Infra-Announce-AI-and-Digital-Financing-Framework-Agreement.

13. CNBC, “OpenAI, Anthropic backer MGX raises one of the biggest AI funds ever as it closes at $49 billion”, 1 July 2026. https://www.cnbc.com/2026/07/01/mgx-ai-fund-uae-49-billion.html.

14. Semafor, “UAE ups pre-IPO stake in Anthropic”,1 June 2026. https://www.semafor.com/article/06/01/2026/uae-ups-pre-ipo-stake-inanthropic.